# ACM Enterprise Management System “Necessity is the mother of invention.”
Project Manager
Andrew Meredith
Project Definition
The design, development and deployment of a database with a usable interface for internal use within ACM.
Project Scope
Membership, sales, accounting, library and pertinent organization documents.
Project Goals
Provide a usable desktop and web-based application for administration of ACM’s membership, sales, accounting, library and pertinent organization documents.
Project Dependencies
1. Modeling and implementation of database and interface
Project Team
1. Andrew Meredith
2. Ariana Aguirre
3. Donald Herman
4. Edgar Ortiz
5. Mike Brown
Project Stakeholders
The Association for Computing Machinery
Project Phases
Planning -> Design -> Development -> Deployment
Project Timeline
1. November – January : Model Database
2. February: Plan database implementation – where it will be, how to access it, what technology to use
3. March – April: Design the database system
4. June: Create the database system.
5. July – mid-August: Test and debug
6. Mid-August: Train every ACM officer on operation of the new system and what they are responsible for
7. Mid-August: Release the database system in the ACM room
Project Challenges
Ensure that all members know their tasks and coordinate with each other during the development and maintenance phases. Managing time between this project, schoolwork, and life (if applicable).